Control & Scheduling

HCI Construction Inc. (“HCI”) utilizes proven techniques to monitor quality and ties the process to each identifiable work item by:

  1. Assigning a schedule activity chain to each item bought or required
  2. Assigning a unique schedule activity to gathering the required submittal information for each item or building element
  3. Assigning a unique schedule activity to the review process for submittal
  4. Assigning a unique schedule activity to the time for fabrication and of every item
  5. Assigning a unique schedule activity to install for all elements or products  per building or project area
  6. Assigning activities for testing of elements and systems as part of on-going quality control
  7. Assigning a unique schedule activity for commissioning of each system to assure building functionality